Appendix H — Acceptance testing
1. General
The Contractor is required to undertake acceptance testing of all pipelines constructed. Acceptance
testing may be done progressively, but must be no earlier than 7 (seven) days after completion of the
section to be tested. Two (2) days notice of acceptance testing should be given to ACTEW as
ACTEW has the right to be present at any acceptance testing being performed. The results of all
acceptance tests must be presented to ACTEW at the time of handover of the assets.
Pipes must be clean before any test is performed. If any of the tests prove
to be unsatisfactory, detect and repair the fault and then re-test (in locating
a fault it is appropriate to isolate the section under scrutiny where its position
can then be detected through the use of appropriate methods). Continue to repair
and re-test until a satisfactory result is obtained. Even if testing produces
satisfactory test results, repair any pipeline or conduit in which there is
a visible or detectable leak or blockage.
A visual inspection shall be carried out to ensure that all sewer lines present a full clean bore, except
where curved sewers are specified on the drawings.
Return to top
2. Air testing general
Air testing of gravity sewer pipes shall be by either pressure testing or vacuum testing. Air testing of
maintenance holes shall be by vacuum testing, air testing of rising mains shall be by pressure testing
only. Prior to tests commencing the Contractor shall nominate either vacuum or pressure testing, and
shall not be permitted to change from one method to the other. The test shall include maintenance
hole drops and house connection branches (service ties).
Return to top
3. Pressure testing of sewers
The sewer to be tested shall be pressurised to the initial pressure specified in Table 2 for a minimum
of 3 minutes to allow the temperature to stabilise.
The pressure shall then be dropped to the test start pressure specified in Table 2. Reaching this
pressure marks the start of the test period.
The pressure shall then be observed for a period of 3 minutes for DN150 and
DN225 sewers, or 5 minutes for DN300 sewers. If the pressure does NOT drop by
more than 5 kPa during this observation period the sewer shall be deemed to
have passed the test.
TABLE 2
Initial sewer pressurisation requirements for dry ground conditions
Depth to sewer invert |
Initial pressure (kPa) |
Test start pressure (kPa) |
Less than 1.5 m |
30 |
25 |
1.5 — 3.0 m |
35 |
30 |
3.0 — 4.5 m |
40 |
35 |
4.5 — 6.0 m |
45 |
40 |
Deeper than 6.0 m |
50 |
45 |
* In water charged ground, pressures are to be increased by 10 kPa for every metre height of water
above the pipe invert.
Return to top
4. Vacuum Ttesting of sewers
A vacuum of 28 kPa shall be drawn from the sewer to be tested. The valve shall then be closed, the
pump turned off and the vacuum gauge monitored for 3 minutes. The sewer under test shall have
passed the test if the vacuum does not fall by more than 5 kPa during the 3 minute period.
Return to top
5. Vacuum testing of maintenance holes
After the maintenance holes have been constructed (including benching and fitting of convertor slab,
surrounding frame and lid) they shall be tested as follows:
- All backfilling shall be completed before testing commences;
- The vacuum test head shall be placed on top of the maintenance hole and the seal inflated (initially
with downward pressure being applied to the maintenance hole tester plate);
- A vacuum of 33.5 kPa shall be drawn on the maintenance hole. The valve shall then be closed, the
pump turned off and the time measured for the vacuum to fall to 30.0 kPa. The maintenance hole
shall have passed the vacuum test if the time taken for this drop exceeds the time specified in
Table 3.
TABLE 3
Maintenance hole vacuum test acceptance times for 3.5kPa vacuum drop
MH depth (m) |
Time (seconds) |
DN1050 MH |
DN1200 MH |
< 2.4 |
17 |
20 |
2.4 — 3 |
21 |
25 |
3 — 4 |
28 |
33 |
4 — 5 |
35 |
41 |
5 — 6 |
42 |
49 |
6 — 7 |
49 |
57 |
Return to top
6. Ovality testing
All DN150 to DN300 PVC, PE and GRP gravity sewer pipes shall be tested with a proving tool to
determine the presence of unacceptable deflections (ovality).
These tests shall be carried out AFTER all vacuum testing is complete and no sooner than 14 days
after all the backfilling operations have been completed.
Testing shall involve pulling a proving tool, for the nominal size pipe shown in Table 4, through each
section of pipe by hand winching to demonstrate that the maximum allowable deflection is not
exceeded.
The proving tool shall comply with the following requirements:
- Be of rigid steel or aluminium alloy fabrication;
- Be non-adjustable;
- Have an odd-number of legs (minimum 9);
- Have an effective length of not less than its nominal diameter (DN);
- Have pulling rings at each end;
- The minimum size (DN) at any point along the length shall be as specified in Table 4;
TABLE 4
Proving tool size
Nominal pipe
size(DN) |
Minimum prover
size (OD) |
PVC (Solid wall) |
PVC (Ultra–rib) |
GRP SN 10000 |
| 150 |
142.6 |
145.8 |
— |
| 225 |
222.9 |
215.7 |
— |
| 300 |
280.8 |
289.2 |
315 |
- Be permanently marked to indicate the nominated pipe size and material, the prover's outside
diameter, the manufacturers name and a unique identification code;
- Have been tested and passed for dimensional compliance by an independent, suitably accredited
testing provider not more than 12 months prior to its use on any main that is to be handed over
to ACTEW.
Sewer pipes that exhibit excessive ovality, by failing the maximum allowable
deflection shown in Table 4 above, shall be replaced and the re-laid section
re-tested for ovality.
Copies of the prover's test certificates shall be submitted to ACTEW upon request
during the construction phase and at the handover inspection.
Return to top
7. Closed circuit TV (CCTV) inspection
ACTEW requires a colour CCTV videotaped inspection of approximately 5% of the length of sewer
mains to be submitted prior to accepting handover. Actual sewer mains to be surveyed will be
nominated by ACTEW just prior to the handover inspection.
Such inspections must be:
- Performed by an appropriately qualified CCTV operator;
- Undertaken in accordance with the guidelines of the Australian Conduit Condition Evaluation
Manual (Reference 5.3);
- Of such quality that an accurate assessment of the internal condition of the sewer can be made.
The following items shall be provided:
- One set of videotapes in VHS, PAL format covering all inspections. Cassettes shall be
appropriately and clearly labelled. This labelling shall include the project description, location, the
date of survey, and the survey agency and Developer involved;
- One set of survey data from the data capture software. This is to be provided in Microsoft Excel
format (or other read compatible) as per Coding Sheet Fig_1 on page 3 of the Australian
Conduit Condition Evaluation Manual (Reference 5.3). Data is to be provided on 3.5 inch
floppy disk media. Disks shall be appropriately and clearly labelled;
- One hardcopy printout of survey data from the data capture software.
Return to top
8. Water mains pressure tests
All water mains, including water services and stop cocks, shall be subjected to a hydrostatic field test
pressure as follows:
- For reticulation pipe work, unless a higher test pressure is specified on the Water Supply Master
Plans, the equivalent of 140 metres head of water at the lowest point within the developed area
of the zone;
- For other pipe work, a test pressure as specified by ACTEW, but not less than the equivalent of
140 metres head of water at the lowest point of the newly constructed works.
It should be noted that the pressure test is intended to detect leakage at operating pressures which
may actually be experienced during the life of the pipe work, not as a test of ultimate pressure
capacity.
Return to top
9. Pressure gauge certification
Pressure gauges used for water and sewer main acceptance testing must have
current (that is, not older than 12 month) certification for accuracy from an
independent, suitably accredited testing provider.
The gauges must be permanently marked to allow them to be identified against the test certificates.
Copies of the gauge certificates must be submitted to ACTEW upon request during
the construction phase and at the handover inspection.
Return to top
10. Product certification requirements
All products used in the construction of the water supply and sewerage systems being handed over to
ACTEW shall meet the requirements of the relevant Australian Standards, and:
- shall be certified as complying with the requirements of the Standards
Australia Product Compliance Program (PCP). Such certification is demonstrated
by complying products carrying a StandardsMark or WaterMark
logo; or
- shall have been appraised by WSAA and approved by ACTEW; or
- shall have been approved by ACTEW.
Evidence of the manufacturer's product certification are to be submitted for ACTEW approval
before ordering. Individual samples or an assembly may be required.
Return to top
11. Test certificate requirements
The Developer is responsible for submitting to ACTEW signed and dated test data records resulting
from scheduled inspections and tests. As a minimum these shall include the following items:
- Project Details: (Project Details common to all certificates)
- Location, Section, Block/s;
- Project Name, Consultant, Contractor;
- Test Location, Date Testing Performed.
- Grading/Compaction Test Certificates (Bedding and Backfill Material):
- Date of Sample, Type of Material;
- Test Location, Compaction Test Depth, Grading Test Results.
- Pressure Test Certificates for Water:
- Pipe Material — Type, Class, Manufacturer, Joint Type;
- Initial Pressure, Test Pressure, Pressure Drop;
- Pressure Gauge Certification Number, Pressure Gauge Certification Date.
- Pressure or Vacuum Test Certificates for Sewer:
- Pipe Material — Type, Class, Manufacturer, Joint Type;
- Pipe grade, Depth to IL, Internal Diameter (Solid Wall), Date of Completion of Backfill;
- Initial Pressure or Vacuum, Test Pressure or Vacuum, Pressure or Vacuum Drop;
- Pressure/Vacuum Gauge Certification Number, Pressure/Vacuum Gauge Certification Date.
- Ovality Test Certificates:
- Pipe Material — Type, Class, Manufacturer, Joint Type;
- Pipe Grade, Depth to IL, Internal Diameter (Solid Wall), Date of Completion of Backfill;
- Prover Size, Prover Identification Number, Prover Certification Details (number and date).
- Vacuum Test Certificates for Maintenance Holes:
- MH number (as per drwg), MH depth;
- Initial Vacuum Reading, Test Vacuum Reading, Duration of Test;
- Vacuum Gauge Certification Number, Vacuum Gauge Certification Date.
- CCTV Inspection:
- Refer to Clause 7 above for CCTV inspection requirements.